Title: Hold a public hearing, and discuss, deliberate and provide staff with direction regarding the proposed site for construction, expansion, and use of an electric power transmission substation generally located in the northeast corner of East Sherman Drive and Hartlee Field Road; as part of Denton Municipal Electric's service territory. [Hartlee Field Substation]
Attachments: 1. Exhibit 1 DME Substations Locations Map, 2. Exhibit 2 Hartlee Field Options Map, 3. Exhibit 3 Revised Yellow Site Option, 4. Exhibit 4 Project Information Sheet
Date Ver.Action ByActionResultAction DetailsVideo
No records to display.

Agenda Information Sheet

 

DEPARTMENT:                     Denton Municipal Electric

 

CM/ ACM:                                          Todd Hileman, City Manager

 

Date:                                                               May 2, 2017                     

 

SUBJECT

Title

Hold a public hearing, and discuss, deliberate and provide staff with direction regarding the proposed site for construction, expansion, and use of an electric power transmission substation generally located in the northeast corner of East Sherman Drive and Hartlee Field Road; as part of Denton Municipal Electric’s service territory. [Hartlee Field Substation]

Body

 

BACKGROUND

The Denton Municipal Electric (DME) Capital Improvement Program includes a project to reconstruct its electric transmission system.  Its current capacity is inadequate for expected future load.  The need for a substation in the vicinity of the above described area (Exhibit 1), in the City of Denton, Texas, has been identified and shared with closely impacted landowner representatives.

 

DME held an open house and meetings to discuss the siting of the proposed substation and transmission routes with the landowner representatives of the potential site area and has received feedback from them.

 

OPTIONS

1.                     Provide staff with direction

 

PRIOR ACTION/REVIEW (Council, Boards, Commissions)

Options were presented in Closed Session to the Public Utilities Board on March 27, 2017, and to the City Council on December 6, 2016. A Public Hearing was held at the Public Utilities Board meeting on April 10, 2017, at which time the PUB recommended the yellow site option. (vote 7-0)

 

STRATEGIC PLAN RELATIONSHIP

The City of Denton’s Strategic Plan is an action-oriented road map that will help the City achieve its vision.  The foundation for the plan is the five long-term Key Focus Areas (KFA):  Organizational Excellence; Public Infrastructure; Economic Development; Safe, Livable, and Family-Friendly Community; and Sustainability and Environmental Stewardship.  While individual items may support multiple KFAs, this specific City Council agenda item contributes most directly to the following KFA and goal:

 

Related Key Focus Area:                       Public Infrastructure

Related Goal:                                                                2.3 Promote superior utility services and facilities

 

EXHIBITS

1.                     DME Substation Locations Map

2.                     Hartlee Field Substation Options Map

3.                     Revised Yellow Site Option

4.                     Project Information Sheet

 

                                                                                                                                                   Respectfully submitted:

                                                                                                                              Phil Williams

                                                                                                                              General Manager

 

Prepared by:

William A. Bunselmeyer