File #: PUB17-098    Version: 1 Name:
Type: Public Utilities Board
File created: 4/14/2017 In control: Public Utilities Board
On agenda: 4/24/2017 Final action:
Title: Consider recommending adoption of an ordinance authorizing the City Manager to execute a water main cost participation agreement between the City of Denton, Texas and Love's Travel Stops & Country Stores, Inc. for the City's participation in the oversizing of water mains and in accordance with the terms and conditions of this ordinance; authorizing the expenditure of funds therefore; and providing an effective date. (In the not-to-exceed amount of $80,322.16)
Attachments: 1. 1. Location Map, 2. 2. Tabulated Calculation of the Oversize Participation Amount, 3. 3. Water Main Cost Participation Agreement, 4. 4. FY 2017 CIP Detail Sheet
Date Ver.Action ByActionResultAction DetailsVideo
No records to display.

AGENDA INFORMATION SHEET

 

 

DEPARTMENT:                     Utilities Administration                     

 

ACM:                                                                Jon Fortune, 8535

 

Date:                                                               April 24, 2017

 

SUBJECT

Title

Consider recommending adoption of an ordinance authorizing the City Manager to execute a water main cost participation agreement between the City of Denton, Texas and Love’s Travel Stops & Country Stores, Inc. for the City’s participation in the oversizing of water mains and in accordance with the terms and conditions of this ordinance; authorizing the expenditure of funds therefore; and providing an effective date.  (In the not-to-exceed amount of $80,322.16) 

Body

 

BACKGROUND

Love’s Travel Stops & Country Stores, Inc. (“Developer”) is in the process of installing approximately 2,532 feet of water line within the City Limits of Denton (see Exhibit 1).  This line is part of the public improvements they are installing as part of their Love’s Travel Stop Development project.  The Development project requires a 12” water line to be installed along I                                              35N from FM 1173 to Barthold Road.  The City sought to oversize the pipeline from a 12” to a 16” in accordance with the City’s oversize participation policies and procedures outlined in the Denton Development Code.  The purpose of the oversize is to increase the water transmission line capacity along the I-35N corridor.  The 16” water line size is consistent with the recently Water Distribution System Master Plan.

 

The Developer presented the City with their tabulated calculation of the Oversize Participation Amount (see Exhibit 2).  Staff has reviewed the entire tabulation and determined that 1) the quantities are correct, and 2) the unit prices are not unreasonable, based on similar work on other recent projects.  Thus, Staff takes no exceptions to the oversize participation cost as prepared by the Developer.  Staff has prepared a corresponding Water Main Cost Participation Agreement (see Exhibit 3).

 

OPTIONS

1.                     Approve the Water Main Cost Participation Agreement as prepared and submitted by Staff.

2.                     Reject the Water Main Cost Participation Agreement.

 

RECOMMENDATIONS

Staff recommends approval of the Water Main Cost Participation Agreement as prepared and submitted. 

 

PRIOR ACTION/REVIEW (Council, Boards, Commissions)

None

 

FISCAL INFORMATION

The City’s financial obligation regarding this item is $80,322.16.  There is $200,000 budgeted for oversize participation in the FY 2017 (see Exhibit 4). 

 

DATE SCHEDULED FOR COUNCIL APPROVAL

This item is scheduled for approval by City Council on May 2, 2017.

 

EXHIBITS

1.                     Location Map

2.                     Tabulated Calculation of the Oversize Participation Amount

3.                     Water Main Cost Participation Agreement

4.                     FY 2017 CIP Detail Sheet