Title: Consider adoption of an ordinance of the City Council of the City of Denton, Texas, a home-rule municipal corporation, providing for, authorizing, and approving the execution by the City Manager, or his designee, of an interconnect agreement between the City of Denton and Enterprise Pipeline Texas, LLC, a Texas limited liability company, in the amount of $1,386,000.00 for the construction of gas supply and metering infrastructure in conjunction with the Denton Energy Center project; approving the execution of such other and further related documents deemed necessary to effectuate this agreement by the City Manager or his designee, which are incident or related thereto; authorizing the expenditure of funds therefore; and providing an effective date. The Public Utilities Board recommends approval (5-0).
Attachments: 1. Fuel Supply Interconnection Approval CC 20170418 FINAL2.pdf, 2. Enterprise Pipeine Ordinance.pdf, 3. Enterprise Pipeline Agreement.pdf
Date Ver.Action ByActionResultAction DetailsVideo
No records to display.

AGENDA INFORMATION SHEET

 

 

DEPARTMENT:                     Denton Municipal Electric

 

CM:                                                               Todd Hileman

 

AGENDA DATE:                     April 18, 2017

 

SUBJECT

Title

Consider adoption of an ordinance of the City Council of the City of Denton, Texas, a home-rule municipal corporation, providing for, authorizing, and approving the execution by the City Manager, or his designee, of an interconnect agreement between the City of Denton and Enterprise Pipeline Texas, LLC, a Texas limited liability company, in the amount of $1,386,000.00 for the construction of gas supply and metering infrastructure in conjunction with the Denton Energy Center project; approving the execution of such other and further related documents deemed necessary to effectuate this agreement by the City Manager or his designee, which are incident or related thereto; authorizing the expenditure of funds therefore; and providing an effective date. The Public Utilities Board recommends approval (5-0).

Body

BACKGROUND

In order to provide a fuel supply for the Denton Energy Center, Denton Municipal Electric will contract with Enterprise Texas Pipeline, LLC to provide the infrastructure necessary to connect the Denton Energy Center to the pipeline owned by Enterprise.  This infrastructure includes the pipeline tap, lateral line, water separator and associated water storage tanks, meters and various types of valves.  Enterprise has extensive experience providing this type of infrastructure to facilities such as the Denton Energy Center. 

 

In accordance with Texas Local Government Code 252.022(a)(14), the procurement of goods purchased by a municipality for subsequent sale by the municipality is exempt from the requirement of competition based selection.  Based upon the Firm’s professional qualifications, expertise, reputation, knowledge of operations and economics, and the existence of the Firm’s main pipeline on the property where the Denton Energy Center is being constructed, staff is of the opinion that Enterprise is a good fit to provide the needed infrastructure. 

 

RECOMMENDATION

Approve a contract with Enterprise Texas Pipeline, LLC in the not-to-exceed amount of $1,386,000.

 

PRINCIPAL PLACE OF BUSINESS

Enterprise Texas Pipeline, LLC

Houston, TX

 

ESTIMATED SCHEDULE OF PROJECT

This agreement will be in effect until all required services are completed or until all authorized funds have been expended.  The estimated completion of construction is in July 2017.

 

FISCAL INFORMATION

The construction services will be funded from Denton Municipal Electric account 603996501.1360.3410.

                                                               

STRATEGIC PLAN RELATIONSHIP

The City of Denton’s Strategic Plan is an action-oriented road map that will help the City achieve its vision.  The foundation for the plan is the five long-term Key Focus Areas (KFA):  Organizational Excellence; Public Infrastructure; Economic Development; Safe, Livable, and Family-Friendly Community; and Sustainability and Environmental Stewardship.  While individual items may support multiple KFAs, this specific City Council agenda item contributes most directly to the following KFA and goal:

 

Related Key Focus Area:                      Public Infrastructure

Related Goal:                                                               2.3 Promote superior utility services and facilities

 

EXHIBITS

Exhibit 1: Presentation

Exhibit 2: Ordinance

Exhibit 3: Interconnection Agreement

 

                                                                                                                                                                        Respectfully submitted:

                                                                                                                                                                        Phil Williams, 349-8487

                                                                                                                                                                        General Manager

 

 

For information concerning this acquisition, contact: Lawrence Collister at 349-8198.