Consider adoption of an ordinance accepting competitive proposals and awarding a contract for pavement markers installation for the City of Denton Traffic Department; providing for the expenditure of funds therefor; and providing an effective date (RFP 6358-awarded to Striping Technology, LP in the three (3) year not-to-exceed amount of $1,500,000).
Body
RFP INFORMATION
This service is used to provide pavement markers for the motoring public and increase public safety on our streets and school zones. RFP #6358 consists of the labor, material, and supervision necessary to complete installations of pavement markers under the direction of the City of Denton Traffic Operations Department. The RFP also covers all administrative and insurance costs incurred by the contractor. This agreement will not guarantee any minimum amounts of pavement markings and will be used on an as needed basis.
Requests for Proposals were sent to 147 suppliers. In addition, specifications were placed on the Materials Management website for prospective suppliers to download and advertised in the local newspaper. Four (4) proposals were received, evaluated and ranked based upon the published criteria shown on Exhibit 1. Based on the evaluation criteria, Striping Technology, LP received the highest evaluated score and was determined to be the best value for the City. A Best and Final Offer was conducted which resulted in a $14,750 savings annually for a three (3) year estimated savings of $44,250.
RECOMMENDATION
Award to Striping Technology, LP in the three (3) year not-to-exceed amount of $1,500,000. Although this service is primarily used by the Traffic and Streets Departments, this amount includes a contingency for other City departments that may require this service.
PRINCIPAL PLACE OF BUSINESS
Striping Technology, LP
Tyler, TX
ESTIMATED SCHEDULE OF PROJECT
This is an initial one (1) year contract with options to extend the contract for two (2) additional one (1) year periods, with all terms and conditions remaining the same.
FISCAL INFORMATION
The pavement markers will be funded from the appropriate department account at the time the installation occurs.
STRATEGIC PLAN RELATIONSHIP
The City of Denton’s Strategic Plan is an action-oriented road map that will help the City achieve its vision. The foundation for the plan is the five long-term Key Focus Areas (KFA): Organizational Excellence; Public Infrastructure; Economic Development; Safe, Livable, and Family-Friendly Community; and Sustainability and Environmental Stewardship. While individual items may support multiple KFAs, this specific City Council agenda item contributes most directly to the following KFA and goal:
Related Key Focus Area: Public Infrastructure
Related Goal: 2.1 Optimize resources to improve quality of City Roadways
EXHIBITS
Exhibit 1: Evaluation and Ranking Sheet
Exhibit 2: Ordinance
Exhibit 3: Contract
Respectfully submitted:
Ethan Cox, 349-7421
Customer Service Manager
For information concerning this acquisition, contact: Galen Gillum at 349-7656.